Mivan Inventory Protocol (Receiving Process)

  • Materials received must be checked by component wise and
    verified with the packing list.
  • Store personnel and MIVAN supervisor and Engineer must be present to monitor the entire material receiving process.
  • All the materials must be received in tonnage.
  • If the receiving site receives damaged materials, then they must inform the centralized yard with proper details and photographs.
  • The receiving site must be, prior to receive the soft-copy of the packing list before the receiving of materials.
  • Receive of material will done through electronically generated challan.
  • All the standard component should be cleaned with scrapper and wire brushes Wire brushes to be used on side rails only and scrapper on concrete contact face.
  • To reduce the cost towards manual cleaning Chemical solution option may be explored.

 

 